MAC meeting 22 January 2025
https://indico.cern.ch/event/1505576/
Rough calendar for 2025
- New calendar
- Finish with hexabords: qualify tooling
- ASICs limit the hexaboard production
- ROC3C sometimes gets blocked by SEU. (Will know more in Feb.)
- New hexaboards in April
- ~100/month from (5 months) April - August
- September - December 200 / month
Tooling Update
- Order 3 (sensor trays) recieved Dec
- Orders 4-7 (sensor PUT / Gantry Tool holder) Est delivery Feb 24
DB Updates
- Slides from Sindhu and Manami
CMU
- Chiller / Two new technicians
- Assembling 2 modules / day for one weeek
- Assembled 6 modules (all look good)
- Change expired wire / calibrate bond force
- Test stand GUI crashing
- Workflow is good.
- Need new tooling to get to 4 / day (~ mid March)
- Almost Finished UCSB action items