MAC meeting 22 January 2025

https://indico.cern.ch/event/1505576/

Rough calendar for 2025

  • New calendar
  • Finish with hexabords: qualify tooling
  • ASICs limit the hexaboard production
  • ROC3C sometimes gets blocked by SEU. (Will know more in Feb.)
  • New hexaboards in April
    • ~100/month from (5 months) April - August
  • September - December 200 / month

Tooling Update

  • Order 3 (sensor trays) recieved Dec
  • Orders 4-7 (sensor PUT / Gantry Tool holder) Est delivery Feb 24

DB Updates

  • Slides from Sindhu and Manami

CMU

  • Chiller / Two new technicians
  • Assembling 2 modules / day for one weeek
    • Assembled 6 modules (all look good)
    • Change expired wire / calibrate bond force
    • Test stand GUI crashing
    • Workflow is good.
    • Need new tooling to get to 4 / day (~ mid March)
  • Almost Finished UCSB action items

Follow-ups